第16回
大間原子力発電所の建設段階における運転訓練シミュレータ導入とSA改造について
著者:
小松 滋,市川 健児,(電源開発)
発刊日:
公開日:
キーワードタグ:
The Ohma Nuclear Power Station, currently under construction, is an ABWR, and is designed to be capable of using MOX fuel in the entire core. Construction commenced in May 2008 and progress has been made, but the overall progress rate of the construction after the Great East Japan Earthquake has been 37.6%. The operation training simulator was installed ahead of other facilities to implement design change information under the new regulatory requirements, and the simulator is being used to conduct training ...
英字タイトル:
Status of Operator training simulator of Ohma Nuclear Power Plant during construction and modification for severe accidents